Case · Nuclear

Reactor core lifting equipment

Centre of gravityLifting pointLifting lugsStatic FEALifting regulationsFabrication drawingsREV ANTSSHEET 1/1
  • EquipmentThree-arm lifting frame with vessel interface
  • DisciplineMechanical design and structural analysis
  • Tools3D model, static structural FEA
  • DeliverableDesign, verification and fabrication drawings

The challenge

Lifting a reactor core demands equipment that distributes load in a controlled way over the vessel interfaces and can be demonstrated, by calculation, within the margins nuclear lifting equipment regulations require.

Scope

  • Solving the lifting problem: pick points, frame geometry and vessel interfaces
  • Mechanical design of the three-arm frame and its joints
  • Finite element structural analysis: equivalent stresses and safety factors
  • Framing the design within the regulations applicable to lifting equipment in nuclear facilities
  • Fabrication drawings and bill of materials

How we worked

From the problem to the equipment, not from the catalogue to the problem. The frame was defined from the actual core and vessel geometry, then verified.

Verification with documented margin. Every critical FEA zone is referenced to the governing code criterion.

Result

Verified, buildable equipment

Lifting frame designed, verified and documented for fabrication, with peak stresses within the admissible limits of the applicable regulations.

See the discipline

Have a project underway?

Tell us the scope and we will tell you what information a quote requires.